Data Center
Data Center

Data Center BIM & AI Integrated Services

We have a deep understanding of the stringent standards and complex requirements of global data center clients, delivering tailored, top-tier services to meet those needs. Leveraging extensive hands-on experience in both design and construction phases, Wyzrs provides solutions that fully comply with EIR (Employer’s Information Requirements) from concept to completion.

Through automated BIM modeling, we enhance productivity and execute coordination processes optimized for complex MEP systems such as power distribution, cooling, fire protection, and network infrastructure. With in-depth knowledge of critical data center equipment such as HVSS, we develop digital twin–based construction strategies that ensure precise integration between architecture, structure, and MEP systems, minimizing construction risks. This approach has enabled us to identify and resolve thousands of potential clashes in advance, eliminating rework, reducing unnecessary costs, and significantly shortening construction schedules.

From these meticulously coordinated BIM models, we generate highly accurate fabrication and installation drawings, ensuring precision in manufacturing and installation. By integrating AI, we improve the accuracy of data analysis and automate repetitive reporting tasks, boosting productivity. Additionally, our reinforcement learning–enhanced 4D simulation strategies reduce scheduling risks and improve the predictability and stability of the entire project timeline. All clash resolution data is incorporated into the as-built digital twin, establishing a smart asset management system that supports long-term operations, maintenance, and future expansion.

rePresentative project info

Owner
Architect
General Contractor
Facade Contractor
Project Duration
Opening Date
Area
Program
No items found.
representative project

AWS Data Center

Location
Incheon, South Korea
Owner

Amazon Web Services INC (Incheon City)

Architect

Chang-Jo Architects

General Contractor

Hyundai E&C Co.

Facade Contractor
Project Duration
Opening Date
Area

44,813 m2 (GFA)
B1F - 8F & 5 Additional Buildings

Program

Internet Data Center

representative project

STT Seoul 1 Gasan Data Center

Location
Gasan (Seoul), South Korea
Owner

STTelemedia Global Data Center Inc.

Architect

Designcamp Moonpark dmp
Junglim Architecture

General Contractor

Hyosung Heavy Industries

Facade Contractor
Project Duration

2022 - 2023

Opening Date
Area

39,590m2 (GFA)
B2F - 10F

Program

Data Center